Fit Out & A&A Works for HKG10 data center at Tseung Kwan O

Client

HKG10 Data Center

Scope

Additions & Alterations, Fit Out

Size

20,000 sq ft

Completion

September 2014

Program Duration

4.5 months

TCG was engaged by BYME Engineering Limited to deliver fit-out and A&A works for a 20,000 sq.ft. data center at Tseung Kwan O. Completed in just 4.5 months, the project included structural demolition, internal upgrades, and the supply and installation of over 300 tonnes of structural steel on the rooftop. The project showcased TCG’s capability in executing complex MEP and structural works under a fast-track programme.