Renovation Works for Training Centre at Terminal 1, HKIA

Client

Hong Kong International Airport

Scope

Fit Out

Size

4,500 sq ft

Completion

November 2020

Program Duration

3.5 months

TCG completed fit-out and MEP works for the renovation of a 4,500 sq.ft. training centre located in Unit 5Z539 of Terminal 1 at Hong Kong International Airport. Delivered within a 3.5-month programme, the project focused on modernising the facility to enhance functionality and user experience. The scope included upgrades to interior finishes and building services, ensuring a high-performance environment aligned with the airport’s operational standards.